OFFICIAL || ECG finally releases 12-hour-per-day dumsor timetable

ECG, Electricity Company, Ghana, Gridco

As part of projects to improve power supply reliability and system voltages, the Ghana Grid Company (GRIDCO) in collaboration with the Electricity Company of Ghana (ECG) will undertake interruptions in power supply to facilitate the work of contractors at various stages and times.

In this regard, the Pokuase Bulk Supply Point (BSP) which is near completion and sponsored by the Millennium Challenge Corporation ( MCC) under the auspices of the Millennium Development Authority (MIDA) will require a tie-in to GRIDCO’s 330kv transmission line.

This exercise will require a complete shutdown of the 330kv line thereby affecting power supply reliability to the Mallam BSP.

In view of this, the Electricity Company of Ghana wishes to inform its cherished customers and the general public that, the tie-in works will take eight (8) days from Monday, 10th to Monday, 17th May, 2021 and will affect power supply to some customers in the North-Eastern parts of Accra.

The affected groups and outage schedule are as follows:

GROUP A

Nsakina, Oduman, Odorkor Oficial Town, Awoshie, Odorgonno, Mallam Abease, Top Base, Kokompe, Zamrama Line, Banana Inn, Chorkor, Korle Gonno, Gbegbeysee, Shiabu, Kwashi-Bu, Abeka Lapaz, Nii Boye Town, Alhaji, Sowutuom, Ablekuma New Town, Dansoman Control Market, GBC Staff Quarters, Old barrier, Opeikuma, Ashalaja, Lamptey Mills

GROUP B

Lower McCarthy, Mallam, Gbawe, Agape Junction, Bubiashie, Demod, Abossey Okai, Santamaria, Bortianor Red Top, New Aplaku, Mataheko, Dansoman SSNIT Flats, Glefe, Nyanyano, Nyanyano Kakraba, Iron City, Breku, Tuba

GROUP C

See also  FDA closes Shoprite's meat section at Accra Mall

Sakaman, Hansonic, Upper McCarthy Hill, Tettegu, Melcom Plus Industrial Area, Abeka Market, Lartebiokorshie, Tantra Hill, Nyamekye, Pokuase ACP Estates, Amasaman, Anyaa, NIC, Nsumfa, Antieku, Bortianor, Wesley Grammar, Ayigbe Town, Korkordzor, Banana Inn, Mamprobi New Town

GROUP D

Odorkor, St. Anthony, Djaman Township, Oblogo, Salaga Market, CMB Flats, Mamprobi, Soko, Taifa, Ofankor, Asofa, Alhaji, Tabora, Chantan, Israel, Fadama, North Kaneshie, Joma, NIC Top, Seminary, Sowutuom Last Stop, Ablekuma Curve, Russia, Sukura, Kokrobite, Bortianor, Osofo Dadzie, Datus

SCHEDULE

GRIDCo Dumsor Timetable

 

Other needed interruptions in power supply to enable contractors complete the different intervention projects, will be communicated in due course.

While calling on customers to bear the inconvenience, the ECG or the Ghana Grid Company (GRIDCo) pledged their commitment to complete the projects on time.

WhatsApp Job & Scholarship Alert

  1. To get daily Job and Scholarship Alerts on Whatsapp, Join Our WhatsApp Group via the link below.

NOTE: PLEASE IF YOU’RE ON ANY OF OUR WHATSAPP GROUPS, DON’T JOIN THIS ONE

CLICK HERE TO JOIN WHATSAPP GROUP

 

Take Note

UNDER NO CIRCUMSTANCE SHOULD AN APPLICANT PAY MONEY TO ANYONE IN GETTING A JOB WE HAVE PUBLISHED 

LEAVE A REPLY

Please enter your comment!
Please enter your name here